Building Plan Permission (New/Additional/Revision/Reconstruction) - Less than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 45
Total number of applications received 6849
Total number of applications approved 2758
Total number of applications Withdrawn/Returned/Rejected 3232
Average time taken to obtain approval 1 mon 32 days
Median time taken to obtain approval 1 mon 22 days
Minimum time taken to obtain approval 3 days
Maximum time taken to obtain approval 1 year 2 mons 22 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 893,508.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - More than 40,000 SQFT
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 90
Total number of applications received 1375
Total number of applications approved 581
Total number of applications Withdrawn/Returned/Rejected 408
Average time taken to obtain approval 4 mons 21 days
Median time taken to obtain approval 4 mons 4 days
Minimum time taken to obtain approval 3 days
Maximum time taken to obtain approval 1 year 2 mons 23 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 1,688,004.00

Building Plan Permission (New/Additional/Revision/Reconstruction) - High Rise Building
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120
Total number of applications received 195
Total number of applications approved 64
Total number of applications Withdrawn/Returned/Rejected 41
Average time taken to obtain approval 5 mons 42 days
Median time taken to obtain approval 6 mons 12 days
Minimum time taken to obtain approval 11 days
Maximum time taken to obtain approval 1 year 1 mon 25 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate 26,486,884.00

Plinth Inspection
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 15
Total number of applications received 323
Total number of applications approved 163
Total number of applications Withdrawn/Returned/Rejected 54
Average time taken to obtain approval 40 days
Median time taken to obtain approval 27 days
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 9 mons 28 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected

Issue of Completion Certification
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 30
Total number of applications received 467
Total number of applications approved 301
Total number of applications Withdrawn/Returned/Rejected 75
Average time taken to obtain approval 29 days
Median time taken to obtain approval 16 days
Minimum time taken to obtain approval 1 day
Maximum time taken to obtain approval 10 mons 3 days
Average fee taken by the Department for completion of entire process of obtaining approval/certificate No fee collected
Change of Land Use Statistics FROM 01.01.2024 TO 31.03.2025
Particulars Details
Time limit prescribed as per the Public Service Guarantee Act 120 days
Total No.of application received 1155
No.of G.O issued 531
No.of application withdrawn/rejected/Returned 157
No.of application pending with applicant 142
No.of application sent to Govt. 89
No.of application in DO pending 145
No.of application in HO pending 91
Average time taken to obtain Government Order 212 days
Minimum time taken to obtain Government Order 84 days
Maximum time taken to obtain Government Order 339 days
Average fee taken by the Department for completion of entire process of obtaining Government Order Rs.20,000/-